Chinese contractor asks to further delay Hanoi's first sky train

The main contractor of Hanoi's first elevated railway line running from Cat Linh to Ha Dong, to the north of Hanoi, has suggested pushing back the project's deadlines to late 2018, according to the Transport Ministry.

Under the new schedule, the project would have test runs in early September 2018, and would be put into operation in November 2018. This would result in an 11-month delay compared to the previously proposed schedule, which would have seen test runs in October this year and a fully operational elevated railway by mid-2018.

"This is only the Chinese contractor's estimation, not an official schedule," said Nguyen Ngoc Dong, vice minister of transport. "The Transport Ministry has tasked the project's management board with reviewing its progress, and would report to the prime minister in January 2018."

The main contractor, the state-owned China Railway Sixth Group Co., claimed delayed disbursment of $250 million in official development assistance (ODA) from China is still the cause of the delay. The main contractor still owes Vietnamese contractors over VND600 billion ($26.5 million), despite already taking over $65 million from its own working capital to pay them.

In October, the project's general manager Tang Hong said he had reported to the Chinese embassy to urge the disbursement as well as worked with the Transport Ministry to speed up the project.

According to Dong, Vietnam has resolved all disbursement issues on its side but the necessary procedures on China's side have yet to be completed.

Currently 95 percent of the project's construction work has been completed, while 60 percent of imported equipments have arrived in Vietnam and 40 percent of equipments have been installed. The contractors are expected to install the project's signal and electronic systems, as well as finish construction of railway stations in the coming months.

Work on the Cat Linh-Ha Dong elevated railway, which will run over more than 13 kilometers (8 miles), started in October 2011 and was originally scheduled for completion in 2013. But several hurdles, including issues with the Chinese contractor, have been stalling the project for years.

The original cost estimate of $552.86 million has also ballooned to more than $868 million, including $670 million in loans from China.



from Tin mới nhất - VnExpress RSS http://ift.tt/2jmvqo8
via IFTTT
Nguyễn Hòa
Nguyễn Hòa

This is a short biography of the post author. Maecenas nec odio et ante tincidunt tempus donec vitae sapien ut libero venenatis faucibus nullam quis ante maecenas nec odio et ante tincidunt tempus donec.

Không có nhận xét nào:

Đăng nhận xét